Project Phases

01June

Phases 4 & 5 (M&E and Interior works)

The work started on 01/06/2018 this phase will cover the mechanical and electrical work including the finishing for the ground level of the centre. Based on contractors contract this phase will take up to 7 months to be completed.


15December

Phase 3: Shell and Fences

The stone work, dome, minaret, doors and windows was completed.

23July

Phase 2: Skeleton

On this stage the work started on the land include the highway work, drainage, steel frame and building the skeleton for all four floors.

23July

Phase 1: Foundation and Leveling

On this stage, all legal works have been done and the land was purchased.

22November

land purchase and legal documentation

Dr Khalid Al-Mathkoor, head of the Supreme Committee for the Implementation of Islamic Sharia in Kuwait, puts the foundation stone for the Emaan Trust